What is a side extension?

A side extension builds into the space beside a semi-detached or detached house, often over a driveway or side passage. It can be single-storey, for a utility room, downstairs toilet or study, or two-storey to add a bedroom above.
How much does a side extension cost in Fareham?
In Fareham, a side extension typically costs £1,900–£2,950 per m² of floor area, including VAT at 20% (standard rate). For a typical 28 m² project that is roughly £53,000–£82,500. Prices across the South East are typically 12% above the UK average for this kind of work, which is reflected in the range for Fareham. Design, structural calculations and council fees are extra.
| Size or type | Guide range |
|---|---|
| Smaller project (20 m²) | £38,000–£59,000 |
| Typical project (28 m²) | £53,000–£82,500 |
| Larger project (39 m²) | £74,000–£115,000 |
| Rate per m² | £1,900–£2,950 |
What moves the price most:
- Single or two storeys
- Internal fit-out of the new rooms
- Drains, gas meters or soil pipes that need moving
- Steel work where the side wall is opened
A guide range is only a starting point: the guide price tool gives an instant figure for your size, and a free survey turns it into a fixed quote.
Do you need planning permission for a side extension in Fareham?
The approval route for Fareham is set by planning law in England. In England a single-storey side extension can be permitted development if it is no more than 4 metres high and no wider than half the width of the original house. Side extensions of more than one storey always need planning permission, as do side extensions in conservation areas, National Parks and National Landscapes.
Where work involves a shared wall, building on the boundary, or digging foundations within 3 metres of a neighbour’s building and deeper than its foundations (or within 6 metres for deeper work), the Party Wall etc. Act 1996 applies and notices must be served before work starts.
Our first visit includes a check of your planning history, so you know the route before paying for drawings.
What we handle
Handled as part of most side extensions:
- Walls, roof and windows to match the house
- Building control completion
- Planning drawings and application
- Survey of the boundary, drains and access
- Foundations and drainage alterations
- Electrics, heating and plastering
How long does it take?
Expect 10 to 16 weeks on site depending on size and storeys. Design and approvals come first and typically take 3 to 4 months, depending on the approval route.
Building in Fareham
Commuter towns across the South East have many 1930s and post-war semis that suit rear extensions and hip-to-gable loft conversions.
Projects in Fareham (PO16) are surveyed in person before we quote, so the price reflects your actual property.
How it works
- 01
Survey and brief
We visit, discuss your ideas and budget, and survey the property or site at no cost.
- 02
Design and pricing
Design options, then a fixed quote based on the chosen drawings and specification.
- 03
Approvals in place
We handle planning, building control and neighbour notices before work starts.
- 04
Construction and completion
We build, put right any snags and hand over the building control certificate.
Questions about side extensions in Fareham
Who approves a side extension in Fareham?
Planning matters in Fareham go to the council covering your address, and the work needs building control approval. We prepare and submit the applications for you.
How much does a side extension cost in Fareham?
In Fareham, a side extension typically costs £1,900–£2,950 per m² of floor area, including VAT at 20% (standard rate). A typical 28 m² project comes to roughly £53,000–£82,500. Your fixed price depends on the survey and drawings.
How close to the boundary can I build?
You can build up to the boundary, but the eaves height near it is limited under permitted development, and planning officers often want a gap at first floor. If you build on or near a shared boundary, party wall rules may apply.
Will I lose my driveway?
A side extension often takes the side drive. We look at whether parking can be kept at the front and whether a dropped kerb is needed.
How long does it take?
Roughly 10 to 16 weeks on site once approvals are in place, depending on whether it is one or two storeys.