Side extensions in Hampstead

We take on side extensions in Hampstead, about 4 miles north-west of central London, handling the drawings, approvals and construction so you deal with one company throughout.

Guide price in Hampstead

£2,200–£3,450 per m² of floor area

In Hampstead, a side extension typically costs £2,200–£3,450 per m² of floor area, including VAT at 20% (standard rate). For a typical 28 m² project that is roughly £61,500–£96,500.

Book a free home visit

Tell us about your project. We reply to arrange a visit and a fixed quote.

Free home visit and measured survey
Fixed price for the agreed specification
Drawings, approvals and build in one contract
Building control sign-off arranged
England, Wales, Scotland and Northern Ireland

What is a side extension?

Two-storey side extension in matching red brick on a semi-detached house with a block-paved drive

A side extension builds into the space beside a semi-detached or detached house, often over a driveway or side passage. It can be single-storey, for a utility room, downstairs toilet or study, or two-storey to add a bedroom above.

How much does a side extension cost in Hampstead?

In Hampstead, a side extension typically costs £2,200–£3,450 per m² of floor area, including VAT at 20% (standard rate). For a typical 28 m² project that is roughly £61,500–£96,500. Building costs in London run about 30% above the UK average, and the figures for Hampstead are adjusted to reflect that. Design, structural calculations and council fees are extra.

Guide prices for Hampstead, including VAT at 20% (standard rate)
Size or typeGuide range
Smaller project (20 m²)£44,000–£69,000
Typical project (28 m²)£61,500–£96,500
Larger project (39 m²)£86,000–£134,500
Rate per m²£2,200–£3,450

Your quote will depend mainly on:

  • Steel work where the side wall is opened
  • Boundary walls and access for materials
  • Roof design and tile matching
  • Single or two storeys

A guide range is only a starting point: the guide price tool gives an instant figure for your size, and a free survey turns it into a fixed quote.

Do you need planning permission for a side extension in Hampstead?

The approval route for Hampstead is set by planning law in England. In England a single-storey side extension can be permitted development if it is no more than 4 metres high and no wider than half the width of the original house. Side extensions of more than one storey always need planning permission, as do side extensions in conservation areas, National Parks and National Landscapes.

Where work involves a shared wall, building on the boundary, or digging foundations within 3 metres of a neighbour’s building and deeper than its foundations (or within 6 metres for deeper work), the Party Wall etc. Act 1996 applies and notices must be served before work starts.

Our first visit includes a check of your planning history, so you know the route before paying for drawings.

What we handle

Handled as part of most side extensions:

  • Electrics, heating and plastering
  • Opening into the existing house
  • Planning drawings and application
  • Structural calculations
  • Building control completion
  • Foundations and drainage alterations

How long does it take?

Allow 10 to 16 weeks on site depending on size and storeys. Before that, surveys, drawings and approvals usually take 3 to 4 months, longer if the council asks for changes.

Building in Hampstead

Space is at a premium in London, so homeowners often build out into the side return or up into the roof rather than move.

We work across Hampstead and neighbouring areas such as Highgate, Golders Green and Camden. Postcodes we cover in Hampstead include NW3.

How it works

  1. 01

    Free visit

    We look at the property, talk through what you want and measure up. There is no charge and no obligation.

  2. 02

    Design and pricing

    Design options, then a fixed quote based on the chosen drawings and specification.

  3. 03

    Permissions sorted

    Applications, building control and neighbour arrangements, all before the start date.

  4. 04

    Build and handover

    Work follows the agreed programme, with inspections along the way and a completion certificate at the end.

Questions about side extensions in Hampstead

How long does it take?

Roughly 10 to 16 weeks on site once approvals are in place, depending on whether it is one or two storeys.

Can a side extension go over a drain?

Often yes, with a build-over agreement from the water company or by rerouting the drain. We check this during the survey.

Do you build side extensions in Hampstead?

Yes. We build side extensions across Hampstead, including postcodes NW3. Every project starts with a free home visit.

How much does a side extension cost in Hampstead?

In Hampstead, a side extension typically costs £2,200–£3,450 per m² of floor area, including VAT at 20% (standard rate). A typical 28 m² project comes to roughly £61,500–£96,500. Your fixed price depends on the survey and drawings.

Can I build a side extension without planning permission?

In England a single-storey side extension can be permitted development if it is no more than 4 metres high and no wider than half the original house, and the house is not in a conservation area or similar protected land. Two-storey side extensions always need planning permission.