What is a structural alteration?

A structural alteration changes how a house carries its loads, most often by removing a load-bearing wall and replacing it with a steel beam. It is how kitchens and dining rooms become open-plan, and how extensions are joined to the original house.
How much does a structural alteration cost in Romford?
In Romford, a structural alteration typically costs £5,750–£12,500 for a typical knock-through with steel beam, including VAT at 20% (standard rate). The guide for Romford reflects typical costs in London, roughly 30% above the UK-wide figure. Design, structural calculations and council fees are extra.
| Size or type | Guide range |
|---|---|
| A typical knock-through with steel beam | £5,750–£12,500 |
| Higher specification | £12,500–£15,500 |
The main things that change the cost:
- Party wall involvement
- Moving radiators, sockets and pipes
- Flush or downstand beam
- Span of the opening
For a figure based on your own measurements, try the guide price tool, then book a free home visit for a fixed quote.
Do you need planning permission for a structural alteration in Romford?
Whether you need planning permission depends on your house and its location in England. In England removing a load-bearing wall does not need planning permission but does need building regulations approval with an engineer’s calculations. If the beam bears on a party wall, a party wall notice must be served.
Where work involves a shared wall, building on the boundary, or digging foundations within 3 metres of a neighbour’s building and deeper than its foundations (or within 6 metres for deeper work), the Party Wall etc. Act 1996 applies and notices must be served before work starts.
Our first visit includes a check of your planning history, so you know the route before paying for drawings.
What we handle
The work we manage on a structural alteration:
- Party wall notices where needed
- Structural engineer’s calculations and drawings
- Making good, plastering and flooring repairs
- Fire protection to the steel
- Building control sign-off
- Temporary propping
How long does it take?
Expect 1 to 2 weeks on site for a typical knock-through. Allow time beforehand for drawings and approvals, usually 6 to 12 weeks.
Building in Romford
Victorian and Edwardian terraces dominate many London streets, which is why side return, wraparound and mansard projects are so common here.
Projects in Romford (RM1) are surveyed in person before we quote, so the price reflects your actual property.
How it works
- 01
Free visit
We look at the property, talk through what you want and measure up. There is no charge and no obligation.
- 02
Design and fixed quote
Drawings, structural calculations and an itemised, fixed price for the agreed specification.
- 03
Approvals
Planning or permitted development confirmation, building regulations and any party wall matters.
- 04
Construction and completion
We build, put right any snags and hand over the building control certificate.
Questions about structural alterations in Romford
Do I need a party wall notice?
In England and Wales, if the beam sits in a party wall, yes.
How do I know if a wall is load-bearing?
Only a survey can confirm it. Walls that carry floor joists, roof loads or walls above are load-bearing. We check on site and the engineer confirms.
How much does a structural alteration cost in Romford?
In Romford, a structural alteration typically costs £5,750–£12,500 for a typical knock-through with steel beam, including VAT at 20% (standard rate). Your fixed price depends on the survey and drawings.
How long does a knock-through take?
Usually 1 to 2 weeks on site, plus a few days for plastering to dry.
Who approves a structural alteration in Romford?
Planning matters in Romford go to the council covering your address, and the work needs building control approval. We prepare and submit the applications for you.