How long does an extension take to build?

Short answer

Allow 4 to 6 months from first visit to completion for a typical single-storey extension: around 6 to 12 weeks for design and approvals and 10 to 14 weeks on site. Double-storey extensions take longer on site, and planning applications add time.

Design and approvals

  • Survey and design: 2 to 6 weeks.
  • Planning application: about 8 weeks for a decision, or a lawful development certificate if it is permitted development.
  • Building regulations drawings and calculations: 2 to 4 weeks.
  • Party wall notices: 1 to 2 months’ notice in England and Wales.

On site

ProjectTypical time on site
Single-storey extension10 to 14 weeks
Double-storey extension14 to 20 weeks
Rear dormer loft conversion6 to 9 weeks
Garage conversion3 to 6 weeks
Orangery8 to 12 weeks

What causes delays?

Long lead times on glazing and kitchens, bad weather during groundworks, unexpected drains or poor ground, and design changes after work starts. We order long-lead items early and agree changes in writing.

Sources and further reading

This guide is general information, not legal or tax advice. Rules change and depend on your property; we confirm what applies to your project at the survey.