What is a side return extension?

A side return extension fills the narrow passage that runs alongside the back addition of many Victorian and Edwardian terraced houses. It widens a galley kitchen into a proper kitchen-diner, usually with a sloping glazed roof to keep the room bright.
How much does a side return extension cost in Maidenhead?
In Maidenhead, a side return extension typically costs £2,600–£3,700 per m² of floor area, including VAT at 20% (standard rate). For a typical 12 m² project that is roughly £31,000–£44,500. The guide for Maidenhead reflects typical costs in the South East, roughly 12% above the UK-wide figure. Design, structural calculations and council fees are extra.
| Size or type | Guide range |
|---|---|
| Smaller project (8 m²) | £21,000–£29,500 |
| Typical project (12 m²) | £31,000–£44,500 |
| Larger project (17 m²) | £44,000–£63,000 |
| Rate per m² | £2,600–£3,700 |
Your quote will depend mainly on:
- Steel beams and propping of the back addition
- Moving drains and soil stacks
- Length of the side return
- Access through the house for materials
Use the guide price tool to see how size and specification change the figure, then ask for a written, itemised quote.
Do you need planning permission for a side return extension in Maidenhead?
Approvals for a side return extension in Maidenhead follow the rules for England. In England a side return infill is treated as a side extension. It may be permitted development if it is single-storey, no more than 4 metres high and no wider than half the original house, but not in a conservation area. Because side returns sit on the boundary, party wall notices are almost always needed.
Where work involves a shared wall, building on the boundary, or digging foundations within 3 metres of a neighbour’s building and deeper than its foundations (or within 6 metres for deeper work), the Party Wall etc. Act 1996 applies and notices must be served before work starts.
If the answer is not clear-cut, we can apply for formal confirmation before you commit to the build.
What we handle
Handled as part of most side return extensions:
- Building control sign-off
- Foundations and drainage, including any build-over agreement
- Party wall advice and notices
- Drawings and planning or permitted development check
- Steel beams to remove the side wall
- Survey of party walls, drains and the existing back addition
How long does it take?
Build time is typically 10 to 14 weeks on site. Before that, surveys, drawings and approvals usually take 3 to 4 months, longer if the council asks for changes.
Building in Maidenhead
The South East has a broad mix of housing, from Victorian terraces in the towns to post-war semis and newer estates, so extension types vary street by street.
Maidenhead sits in Berkshire, about 12 miles north-east of Reading. We cover the whole of Maidenhead, including postcodes SL6.
How it works
- 01
Survey and brief
We visit, discuss your ideas and budget, and survey the property or site at no cost.
- 02
Design and pricing
Design options, then a fixed quote based on the chosen drawings and specification.
- 03
Approvals
Planning or permitted development confirmation, building regulations and any party wall matters.
- 04
Construction and completion
We build, put right any snags and hand over the building control certificate.
Questions about side return extensions in Maidenhead
Is a glass roof too hot or cold?
Modern solar-control double or triple glazing reduces glare and heat loss. Building regulations also limit how much glazing you can have unless the design shows it performs well enough.
How much space does a side return add?
Typically 1.5 to 2.5 metres of width along the back addition. It often turns a narrow galley kitchen into a family kitchen-diner.
Will I need a party wall agreement?
Almost certainly in England and Wales, because side returns sit on or near the boundary. Notices must be served before work starts, and a party wall surveyor may be appointed if the neighbour does not consent.
How much does a side return extension cost in Maidenhead?
In Maidenhead, a side return extension typically costs £2,600–£3,700 per m² of floor area, including VAT at 20% (standard rate). A typical 12 m² project comes to roughly £31,000–£44,500. Your fixed price depends on the survey and drawings.
How long does a side return extension take in Maidenhead?
Typically 10 to 14 weeks on site. Design and approvals beforehand usually take 3 to 4 months.